Archive: October 2026 Highlight Report and Forward Schedule

The Project Office › Archive › October 2026 Highlight Report and Forward Schedule

Archived 21 October 2026. Copied from the Legal Wiki (page 2581, last modified 2026-10-21), where PRINCE2 records were kept until 21 October 2026. Kept word for word, except that personal names and contact details are replaced. Current product: see the product set.

This material now lives at https://projects.bucklerfamily.estate/highlight-report-october-2026/.

Page ID: 2581 · Title: October 2026 Highlight Report and Forward Schedule · Evidence status: Not yet labelled — see the Editing Protocol · Version: 1.1.0 · Editing Protocol

October 2026 — status and forward schedule at 19 Oct — current baseline, 19 Oct 2026

Current baseline, 19 Oct 2026 (PM File v0.1). Where earlier sections on this page differ, this one governs; they are kept as history.

Latest report: HR-02 (19 Oct). Forward schedule: Project Plan — key dates.

Next 30 daysItem
20–23 Oct24 emails, one body per day
21 OctWG combined reply
22 OctLCC meeting, Item 10
26–28 OctWales Office, Vale, HMLR SAR due
6 NovATISN 26-0009 due; HMLR exception trigger
13 NovICR full complaint target

October 2026 Highlight Report

PRINCE2-style monthly highlight for the Great House Farm evidence programme. Fact-finding and records access continue. The detailed management baseline for this period is the October 2026 Highlight Report under Project Management.

Progress this period

Key outstanding statutory clocks

Forward schedule (next 30 days)

ROLE-PGM / ROLE-PM. Last updated 16 October 2026.

Change history is maintained on the Master Change Log; no separate page-local version footer is maintained.

Page version & change log

Current version: 1.1.0

VersionDate (UTC)Editor (human or agent name)ChangeSource / evidence
1.1.02026-10-19T21:10Zthe Executive’s Tab agentAdded current baseline section (19 Oct 2026): Status pointer and 30-day forward schedule at 19 Oct; earlier content keptOwner, 21:59 BST 19 Oct 2026 (PRINCE2 update and PM File); sources: send-readiness list, 19 Oct WG letters, research cycle 14, task ledger

Agents and editors: follow the Editing Protocol.

PRINCE2 7 outlines: sources · product set · archive