FieldEntry
Date18 Oct 2026
Period5 Oct (last report, 1348) – 18 Oct 2026
StageS0; next gate G0, 18 Dec 2026
OverallAMBER (PM assessment): deadlines in hand; key HMLR copies not yet ordered

Products completed this period

Products planned next period

DateActionOwner
20 OctCouncil reply on meeting format (asked by 17:00)Clerk (Paul Egan)
20 OctCommunity drop-in, Cllr George Carroll, Merrie Harrier, 19:00the Executive / family
22 OctLlandough CC meeting, Item 10, 19:00the Executive
26 OctDue: IR/26/16; ATISN 27589; Vale 00211557Wales Office; WG; Vale
28 OctDue: HMLR subject access request; MoD escalation controlHMLR; MoD
29 OctMeeting minutes, outcome and lessons publishedthe Executive / Tab
19 OctOrder HMLR OC2 copies (C-01 to C-06)the Executive
21 OctRetrieve 1965 conveyance from the Executive’s inbox; add to EV-0042the Executive
19 OctSupply damages inputs (DMG-IN; I-015 to I-019)the Executive

Tolerance status

TypeStatus
TimeWithin; ICR date basis unconfirmed (I-010)
CostWithin: £14 per copy spent (C-21); £83 minimum next
ScopeChanged by CH-004 (approved)
QualityWithin after I-008, I-012, I-013
RiskR-002, R-007, R-008 high impact
BenefitTBC — the Executive to set

Requests for change

Open: CH-009 footer policy; CH-011 WordPress plan. Change Control.

Questions for the Executive

Damages inputs for 5298 (task DMG-IN; risk R-013):

Key issues and risks

Lessons

L-006 to L-009 (Lessons Log).