End Stage Report: S0 (interim)

The Project Office › Parcel A (Phase 1) › End Stage Report: S0 (interim)

Interim. Stage S0 ends at gate G0 (18 December 2026); this report is completed then (activity T24, 16 December).

Project manager’s report

Products against plan at 19 Oct

S0 start-up and initiation, 16 Oct – 18 Dec 2026, in progress since 16 Oct.

ProductPlanActual
Management set18 OctDone 18 Oct; updated 19 Oct
Evidence RegisterOngoingEV-0001 –0243
Free-admin requestsFrom 20 Oct24 scheduled; 26 held with reasons
HMLR copiesVia SAR, due 28 OctWaiting
ICR full complaint13 NovNot started
Legal triageBefore any court stepNot engaged

Review of the business case

Justified for S0

Still justified for S0 (option 1, free routes, £0). Reviewed at G0: reopen decision or “not yet”.

Benefits achieved to date: none measured yet. Residual benefits: B-01 to B-05 (Business Case). Aggregated risk exposure: see the Risk Register.

Review of project objectives

Within proposed tolerances

Time, cost, scope and quality within the proposed tolerances at 19 Oct. Tolerances are not yet agreed by the Project Board.

Review of stage objectives

At G0

To be completed at G0.

Review of team performance

At G0

To be completed at G0.

Review of products

Quality and approval records

Quality records

Quality Register.

Approval records

Management set: Executive acceptance not yet recorded.

Off-specifications

Issue Register.

Phased handover

Not applicable.

Summary of follow-on action recommendations

At G0.

Lessons

Lessons Log

L-001 to L-017 and PL-01 to PL-18 (Lessons Log).

Issues and risks

8 carried forward

Carried forward: R-008, R-017, R-018, R-019, R-022; I-025, I-026; I-032.

Forecast

At G0

To complete at G0: products delivered and accepted; final tolerance position; Business Case review; S1 Stage Plan and costs for approval.