Highlight Report HR-E01

The Project Office › Digital estate › Highlight reports › HR-E01

Project Manager to the Executive (Project Board). Digital estate, 19–20 October 2026.

Date

20 October 2026

20 October 2026

Period covered

19–20 October 2026

19–20 October 2026

Status summary

GREEN. Stage S0 (discovery and inventory) complete; S1 (independence and consolidation) in progress, on time, no spendin

GREEN. Stage S0 (discovery and inventory) complete; S1 (independence and consolidation) in progress, on time, no spending.

This reporting period

4 products completed

Work packages pending authorisation

  • WP-E4: Executive decision on slimming the hosted wiki.

Work packages in execution

  • WP-E3: campus library building check and e-book sub-building.

Work packages completed

  • WP-E1: every link to the hosted wiki removed from this site.
  • WP-E2: estate-level brief, business case, PID, registers, roles and reports.

Products completed in the period

  • Cloudflare and GitHub inventory; wasted preview builds removed; a status page added.
  • Privacy sweep across 40 public sites and 67 PDFs; two personal documents taken off the image library.
  • Internet Archive inventory: 6,132 public addresses across 39 hosts.
  • Asset register: 81 configuration items; 47 live, 7 down, 1 error at first check.

Products planned but not started or completed in the period

None this period.

Corrective actions taken during the period

None this period.

Next reporting period

2 entries

Work packages (to be authorised, in execution, to be completed)

  • S2 preparation: export plan for each data store; triage of the down addresses; library restore plan.

Products to be completed in the next period

  • Redacted e-book edition on the campus shop page.

Corrective actions to be completed during the next period

None this period.

Project and stage tolerance status

Tolerances not yet agreed by the Project Board
Tolerance areaTolerance setStatus this period
TimeNot yet agreed by the Project BoardWithin.
CostNot yet agreed by the Project BoardWithin: no spending.
QualityNot yet agreed by the Project BoardWithin.
ScopeNot yet agreed by the Project BoardUnchanged.
BenefitsNot yet agreed by the Project BoardNot assessed.
RiskNot yet agreed by the Project BoardR-02 scored 16, escalated (below).
SustainabilityNot yet agreed by the Project BoardNot assessed.

Requests for change

0 raised · 0 decided · 0 pending

Raised

None this period.

Approved or rejected

None this period.

Pending

None this period.

Key issues and risks

5 items
  • Backups (R-02, score 16): Internet Archive saving needs an archive.org account.
  • Privacy (R-03): old Git history still holds redacted data.
  • I-01: research.bucklerfamily.estate answers 500.
  • I-02: seven addresses down.
  • Decisions needed from the Executive: archive.org account; Git history purge (permanent); research importer cadence; slimming the hosted wiki; the seven down addresses.

Lessons report (if appropriate)

Not required

Not required this period.

PRINCE2 7 outlines: sources · product set · archive