Highlight Report HR-E02

The Project Office › Digital estate › Highlight reports › HR-E02

Project Manager to the Executive (Project Board). Digital estate, 21 October 2026.

Date

21 October 2026

21 October 2026

Period covered

21 October 2026

21 October 2026

Status summary

AMBER. S1 in progress. Header v2 rolled out on this site; programme phases and the membership pilot added; the PRINCE2 p

AMBER. S1 in progress. Header v2 rolled out on this site; programme phases and the membership pilot added; the PRINCE2 pages are being rebuilt to the official PRINCE2 7 outlines after the Executive found them off-standard. No spending.

This reporting period

4 products completed

Work packages pending authorisation

None this period.

Work packages in execution

  • Rebuild of this site to the PRINCE2 7 management product outlines.
  • Removal of generated heraldry from the directory and the shop.
  • Site health check across the estate.
  • E-book library.

Work packages completed

None this period.

Products completed in the period

  • Header v2.0.3 on this site: loader at the end of the head so the bars appear before first paint (03:05 and 03:37).
  • Clarification of the 1969 transfer on the case pages (01:40).
  • Cedwyn Estate programme phases and the membership pilot pages (15:47).
  • Cedwyn Estate directory live.

Products planned but not started or completed in the period

  • WP-E3 campus library and e-book sub-building: no completion recorded.

Corrective actions taken during the period

  • PRINCE2 pages found to use invented headings; rebuild started to the official PRINCE2 7 outlines (Executive, 18:23 BST).

Next reporting period

2 entries

Work packages (to be authorised, in execution, to be completed)

  • Finish and verify the PRINCE2 7 rebuild; record the product set.

Products to be completed in the next period

  • Executive decisions from HR-E01 still open.

Corrective actions to be completed during the next period

None this period.

Project and stage tolerance status

Tolerances not yet agreed by the Project Board
Tolerance areaTolerance setStatus this period
TimeNot yet agreed by the Project BoardWithin.
CostNot yet agreed by the Project BoardWithin: no spending.
QualityNot yet agreed by the Project BoardExceeded on the PRINCE2 pages (invented headings); corrective action in progress.
ScopeNot yet agreed by the Project BoardMembership pilot added under Phase 2 at the Executive’s request.
BenefitsNot yet agreed by the Project BoardNot assessed.
RiskNot yet agreed by the Project BoardUnchanged.
SustainabilityNot yet agreed by the Project BoardNot assessed.

Requests for change

1 raised · 0 decided · 1 pending

Raised

  • Membership pilot (Executive, 21 Oct): recorded as a Phase 2 project brief.

Approved or rejected

None this period.

Pending

  • Decisions from HR-E01 (archive.org account, Git history purge, hosted wiki, down addresses).

Key issues and risks

2 items
  • Quality: management products must follow the official outlines; the rebuild is the response.
  • R-02 backups and R-03 Git history unchanged.

Lessons report (if appropriate)

1 lessons
  • Use the official PRINCE2 7 product outlines from the start; mark empty fields rather than inventing content.

PRINCE2 7 outlines: sources · product set · archive