Stage Plans (digital estate)

The Project Office › Digital estate › Stage Plans (digital estate)

S0 complete; S1 (independence and consolidation) is the current stage.

Plan description

S0 complete · S1 in progress · S2, S3 planned
StageDatesProductsExit criteriaStatus
S0 Discovery & inventory19–20 Oct 2026Cloudflare/GitHub inventory and rebalance; privacy sweep of all public sites; Internet Archive inventory (6,132 addresses); this registerRegister complete; privacy sweep completeComplete (20 Oct 2026)
S1 Independence & consolidation20 Oct – 1 Nov 2026This site independent of the hosted wiki; estate-level PID and registers; campus with a building for every live site (incl. library and e-book); decision on slimming the hosted wiki to stubsNo link from this site to the hosted wiki; campus complete; Executive decision recordedIn progress
S2 Resilience2 – 15 Nov 2026Internet Archive saves of every public page; exports of each D1/KV/R2 store; credential rotation; triage of the down addresses; restore the library site from its good commit; decision on the Git history purgeEvery Git site rebuildable; every data store exported; archive saves recordedPlanned
S3 Publishing & sustainability16 – 30 Nov 2026Redacted e-book edition and shop; library and Farmbook upkeep; routine monthly register checkPublication checks pass; routine in placePlanned

Plan prerequisites

Mandate

Executive’s mandate of 20 October 2026.

External dependencies

Platform accounts

GitHub, Cloudflare, the hosted wiki and Google accounts held by the Executive; an archive.org account (decision pending).

Planning assumptions

Free plans

Hosting stays on free plans except existing paid storage.

Lessons incorporated

From the Lessons Log

Lessons Log: full local build before every push.

Monitoring and control

Weekly

Highlight report at least weekly; live re-check of the register at each report.

Budgets

£0

£0 beyond existing plans.

Tolerances

Proposed

Not yet agreed by the Project Board. Proposed in the PID.

Product descriptions

PBS

Schedule (S1 work packages)

WP-E1 to WP-E4
  • WP-E1: remove every link to the hosted wiki from this site; group the case pages under Workstream: evidence recovery . Done 20 Oct 2026.
  • WP-E2: estate-level mandate, business case, PID, registers, roles, reports. Done 20 Oct 2026.
  • WP-E3: campus library building check and e-book sub-building by the Wayback archive. 20 Oct 2026.
  • WP-E4: Executive decision on slimming the hosted wiki.

PRINCE2 7 outlines: sources · product set · archive