Highlight Report HR-06 · Ministry of Justice

The Project Office › Highlight Reports › HR-06 › Ministry of Justice

Project Manager to the Project Board. Correspondence with Ministry of Justice against the statutory deadline or the body's own published standard. Working days exclude weekends and England & Wales bank holidays; the day after receipt is day 1. Tap a section to open it.

Date

22 October 2026

22 October 2026

Period covered

19–23 October 2026

Week commencing 19 October 2026 (19–23 October; reported 22 October 2026, 15:30)

Status summary

RED. 1 red house (no reply by the due date), 0 red fish (late or questions left open), 0 on time, 0 not yet due.

RED. 1 red house (no reply by the due date), 0 red fish (late or questions left open), 0 on time, 0 not yet due.

Markers are shown on the body's own route on the dartboard. Source: failures ledger of 22 October 2026 (every entry cites its Gmail message, rule and policy link).

This reporting period

2 items completed
  • Every request thread with this body set against its legal or published due date (failures ledger, 22 Oct 2026).
  • 1 marker placed on this body's ramp layout on the dartboard (red house / red fish, tap for detail).

Next reporting period

0 due date(s) ahead

Due dates not yet reached:

None.

Planned sends (HubSpot task due date = “SCHEDULE SEND” date; nothing is sent without the Executive's order):

No send-email task exists for this body yet; a re-ask awaits the Executive's decision.

Project and stage tolerance status

Time: 1 outside tolerance · Cost: £0

Time: each request has a statutory deadline (FOIA s.10, EIR reg 5(2)/11(4), UK GDPR Art 12(3)) or the body's own published standard. 1 of 1 requests with this body are outside that tolerance.

Cost: £0 spent; free routes first.

Scope: unchanged.

Requests for change

None

None this period.

Key issues and risks

1 issue(s)
MarkerRequestSentDueRepliedWorking days overRule or published standardQuestions still open
Red houseInternal review of the 2025 not-held response (WDTK 'BP vs Buckler 1987' (FOI 250628005) IR)20 Jun 202617 Jul 2026none68s.45 Code of Practice: review within 20 working days, 40 at most1

Each marker is an issue on the issue register with its due date. The risk carried forward: an answer that never arrives closes off later routes (review, regulator, tribunal) unless each step is taken in time.

Lessons report (if appropriate)

2 lessons
  • Count from the first documented date in the record when the original send date is not held; record what would close the gap.
  • Read the whole thread and the body's route before any further draft; one email per body carries every outstanding item.