Highlight Reports

The Project Office › Parcel A (Phase 1) › Highlight Reports

One report per reporting period, from the Project Manager to the Project Board, each with the PRINCE2 7 highlight report sections in order. Reports before October 2026 are retrospective reconstructions.

Also: Checkpoint Report CR-2026-10-21 · Prospective fraud triggers to reopen the case · Decisions awaiting the Executive

Reports, newest first

17 reports · latest HR-05, 21 October 2026
ReportPeriod coveredStatus
HR-0521 October 2026, 18:30–21:30AMBER
HR-0421 October 2026 (to 18:30)AMBER
HR-0320 October 2026AMBER
HR-0218–19 October 2026AMBER
HR-015–17 October 2026AMBER
HR-2026-10A29 September – 4 October 2026AMBER
HR-2026-091–28 September 2026Reconstructed
HR-2026-081–31 August 2026Reconstructed
HR-2026-071–31 July 2026Reconstructed
HR-2026-061–30 June 2026Reconstructed
HR-2026-051–31 May 2026Reconstructed
HR-2026-041–30 April 2026Reconstructed
HR-2026-031–31 March 2026Reconstructed
HR-2026-021–28 February 2026Reconstructed
HR-2026-011–31 January 2026Reconstructed
HR-2025-121–31 December 2025Reconstructed
HR-2025-111–30 November 2025Reconstructed

What each report contains

The PRINCE2 7 outline, section by section
  • Date
  • Period covered
  • Status summary
  • This reporting period: work packages (pending authorisation, in execution, completed); products completed; products planned but not started or completed; corrective actions taken
  • Next reporting period: work packages; products to be completed; corrective actions
  • Project and stage tolerance status (time, cost, quality, scope, benefits, risk, sustainability)
  • Requests for change: raised, approved or rejected, pending
  • Key issues and risks
  • Lessons report (if appropriate)

Source: PRINCE2 7 management product outline for the highlight report. Sources.

Other projects’ highlight reports

Digital estate

PRINCE2 7 outlines: sources · product set · archive