Highlight Report HR-2026-01
The Project Office › Parcel A (Phase 1) › Highlight Reports › HR-2026-01
- Date 31 January 2026 (reconstructed)
- Period 1–31 January 2026
Retrospective reconstruction, written in October 2026 from the dated records-access chronology and backdated to the end of the period. No formal highlight report was issued at the time.
Date
31 January 2026 (reconstructed)
31 January 2026 (reconstructed)
Period covered
1–31 January 2026
1–31 January 2026
Status summary
Two results: direct contact with Cadw failed (both public addresses bounced), and the HM Land Registry title investigation began.
This reporting period
1 entries
Work packages
Pending authorisation
None this period.
In execution
- Records access: correspondence with public bodies and archives (no work package was formally authorised before 19 October 2026). Dated events:
- 23 Jan 2026 · Cadw FOI: request sent to both public Cadw addresses; both bounced
- 29 Jan 2026 · HM Land Registry: application concerning the interest left out at first registration
Completed in the period
None this period.
Products completed in the period
None this period.
Products planned but not started or completed in the period
None this period.
Corrective actions taken during the period
None this period.
Next reporting period
3 entries
Work packages (to be authorised, in execution, to be completed)
None this period.
Products to be completed in the next period
- Follow the HM Land Registry retrieval route and record holding replies.
- Pursue The National Archives route.
- Use each answer to identify the next repository rather than closing at the first refusal.
Corrective actions to be completed during the next period
None this period.
Project and stage tolerance status
Tolerances not yet agreed by the Project Board
No tolerances had been set; no Project Board existed for the period.
Requests for change
0 raised · 0 decided · 0 pending
Raised
None this period.
Approved or rejected
None this period.
Pending
None this period.
Key issues and risks
2 items
- Contact-channel reliability is a measurable risk.
- The registration history cannot be fully tested without the historic first-registration files.
Lessons report (if appropriate)
None
No lessons report this period.
← HR-2025-12 · All highlight reports · HR-2026-02 →