Highlight Report HR-06 · The National Archives

The Project Office › Highlight Reports › HR-06 › The National Archives

Project Manager to the Project Board. Correspondence with The National Archives against the statutory deadline or the body's own published standard. Working days exclude weekends and England & Wales bank holidays; the day after receipt is day 1. Tap a section to open it.

Date

22 October 2026

22 October 2026

Period covered

19–23 October 2026

Week commencing 19 October 2026 (19–23 October; reported 22 October 2026, 15:30)

Status summary

RED. 2 red houses (no reply by the due date), 0 red fish (late or questions left open), 0 on time, 1 not yet due.

RED. 2 red houses (no reply by the due date), 0 red fish (late or questions left open), 0 on time, 1 not yet due.

Markers are shown on the body's own route on the dartboard. Source: failures ledger of 22 October 2026 (every entry cites its Gmail message, rule and policy link).

This reporting period

3 items completed
  • Every request thread with this body set against its legal or published due date (failures ledger, 22 Oct 2026).
  • 2 markers placed on this body's ramp layout on the dartboard (red house / red fish, tap for detail).
  • HubSpot send-email tasks merged to one per recipient (139 → 110 estate-wide); an “Outstanding from earlier correspondence” section added to this body's task, re-asking each open question word for word; planned send date set per the 22 Oct drafts SOP. Nothing sent.

Next reporting period

1 due date(s) ahead

Due dates not yet reached:

RequestDueRule
Review of the 23 Sep disclosure (CAS-347296-M0V4Y1 (review))4 Nov 2026FOIA s.10(1)

Planned sends (HubSpot task due date = “SCHEDULE SEND” date; nothing is sent without the Executive's order):

TaskToPlanned sendBasis
HubSpot task 529430250699RESO records enquiries5 Nov 2026draft already sent 19 Oct 2026; outstanding items travel in the next email to the body
HubSpot task 531096294626FOI team5 Nov 2026forensic assessment only after the body's open deadlines (CAS-347296 review due 4 Nov)

Project and stage tolerance status

Time: 2 outside tolerance · Cost: £0

Time: each request has a statutory deadline (FOIA s.10, EIR reg 5(2)/11(4), UK GDPR Art 12(3)) or the body's own published standard. 2 of 3 requests with this body are outside that tolerance.

Cost: £0 spent; free routes first.

Scope: unchanged.

Requests for change

None

None this period.

Key issues and risks

2 issue(s)
MarkerRequestSentDueRepliedWorking days overRule or published standardQuestions still open
Red houseFOI via WhatDoTheyKnow (WDTK 'Great House Farm, Llandough, Cardiff')2 Sep 202630 Sep 2026none16FOIA s.10(1)1
Red houseInternal review (CAS-356384-B2F5L9)23 Sep 202621 Oct 2026none1s.45 Code of Practice: 20 working days1

Each marker is an issue on the issue register with its due date. The risk carried forward: an answer that never arrives closes off later routes (review, regulator, tribunal) unless each step is taken in time.

Lessons report (if appropriate)

2 lessons
  • Count from the first documented date in the record when the original send date is not held; record what would close the gap.
  • Read the whole thread and the body's route before any further draft; one email per body carries every outstanding item.

PRINCE2 7 outlines: sources · product set · all highlight reports