Stage Plan: S0 (current) and S1 (outline)

The Project Office › Parcel A (Phase 1) › Stage Plan: S0 (current) and S1 (outline)

Stage S0 (start-up and initiation) is the current management stage. The S1 plan is an outline until gate G0.

Plan description

S0, 16 Oct – 18 Dec 2026

S0, 16 Oct – 18 Dec 2026. Objective: Initiation products baselined; key title documents obtained; ICR complaint filed; G0 decision.

Products: Mandate, Brief, PID, Business Case, Plan, Registers (done 18 Oct, review to be confirmed by the Executive ); Form 1C analysis; ICR complaint; End Stage Report.

Status at 19 Oct: AMBER: on time; HMLR copies and legal triage not yet in hand.

Plan prerequisites

2 prerequisites
  • Project Brief and Project Plan (draft).
  • Executive’s “free admin first” instruction (18 Oct).

External dependencies

3 dependencies
  • HM Land Registry subject access reply (due 28 Oct) for the first-registration documents.
  • Replies from public bodies to the requests sent 19–23 Oct.
  • Written legal advice before any court step (DEP-03).

Planning assumptions

2 assumptions
  • Free routes are answered within their statutory periods.
  • No spending in S0 unless the Executive approves it.

Lessons incorporated

From the Lessons Log
  • Free routes before paid copies (CH-012, CH-013).
  • Read replies before chasing; no repeat requests while one is pending.

Monitoring and control

Highlight reports and checkpoints
  • Research cycle every 6 hours with an update to the Executive.
  • Highlight reports: Mon 2 Nov and Mon 7 Dec 2026 (plus the October reports already issued).
  • End Stage Report S0 by 16 Dec; G0 on 18 Dec.

Budgets

£0 spent in S0

S0: £0 cash until free routes are answered. Proposed S0 envelope £0–£800, each spend approved by the Executive. No spend in S0 to date.

Tolerances

Proposed; not yet agreed

Not yet agreed by the Project Board. Proposed: Statutory dates 0 days; plan +5 working days; £0 until free routes answered.

Product descriptions

PD-01 to PD-09

Schedule

S0 activities to G0

S0 activities (status at 19 Oct)

IDActivityOwnerFinishStatus 19 Oct
T05Research flywheel, update after each cycleProject Manager18 DecRunning; cycle 14 done
T05aSend flywheel: 24 READY emailsProject Manager23 OctScheduled from 20 Oct 09:20
T05bWG combined reply drafted, superseding old WG/Cadw draftsProject Manager20 OctIn progress
T05cDebrief run #1; SOP writtenProject Manager19 OctIn progress
T06Clerk reply on meeting formatClerk20 Oct 17:00Waiting; reminder set
T07Briefing, Cllr Carroll, 19:00Executive20 OctPlanned; reminder set
T09LCC meeting, Item 10Executive22 OctPlanned; reminder set
T11HMLR SAR dueHMLR28 OctWaiting
T12Minutes, outcome, lessons publishedProject Manager29 OctPlanned
T13LCC s.12: narrow or reviewExecutiveAfter 22 OctNot started
T15HMLR copies or refusalHMLR6 Nov (exception trigger)Waiting
T16Form 1C analysis; title chainProject ManagerT15 + 3 daysNot started
T20Heneb complaint outcomeHeneb3 NovWaiting
T21ICR full complaintExecutive; Project Manager drafts13 NovNot started
T23Legal triage before any court stepExecutiveBefore any court stepNot engaged
T24End Stage Report; S1 plan; Business Case updatePM16 DecNot started
T25G0Executive18 DecPlanned

S0 detail

IDActivityOwnerFinishPredStatus
T01Project Mandate issuedExecutive16 Oct—Done
T02Project Brief draftedPM16 OctT01Done; acceptance to be confirmed by the Executive
T03PRINCE2 management set rebuiltPM (Project Manager)18 OctT02Done; review to be confirmed by the Executive
T04Evidence Register, 210 EV pagesProject Manager18 Oct—Done
T05Research flywheel cycle every 6 h, each with an update to ExecutiveProject Manager18 Dec—Running
T06Council reply on meeting format (asked by 17:00)Clerk (Paul Egan)20 Oct—Waiting; sent? to be confirmed by the Executive
T07Community drop-in, Cllr George Carroll, Merrie Harrier, 19:00Executive / family20 Oct—Planned
T08Cadw complaint: chase if no stage-one outcomeExecutive20 Oct—Planned
T09Llandough CC meeting, Item 10, 19:00Executive22 OctT06Planned
T10Due: IR/26/16; ATISN 27589; Vale 00211557Wales Office; WG; Vale26 Oct—Waiting
T11Due: HMLR subject access request; MoD escalation controlHMLR; MoD28 Oct—Waiting
T12Meeting minutes, outcome and lessons publishedExecutive / Project Manager29 OctT09Planned
T13s.12 next step: narrow to 2002–2006 or internal reviewExecutiveTBCT09Not started
T14Order HMLR OC2 copies (C-01 to C-06)Executive19 Oct—Not started
T15HMLR copies receivedHMLRTBCT14—
T16Analyse Form 1C and certificate; update title chain (AC-006)Project ManagerT15 + 3dT15Not started
T17Retrieve 1965 conveyance from the Executive’s inbox; add to EV-0042Executive21 Oct—Not started
T18DB/E/1–2 plan 19 and terrier: order (£17) or proxy photographyExecutiveTBC—Not started
T19VG41 register sheet requestedExecutiveTBC—Not started
T20Heneb complaint outcome (five-week aim)Heneb3 Nov—Waiting
T21ICR full complaint (ICR/090/26) drafted and filedExecutive; Project Manager drafts13 Nov (target)T16Not started
T22ICR window control; outer date about 25 NovExecutive18 NovT21Control
T23Legal advice: route triage before any court stepExecutive; adviser to be confirmed by the ExecutiveBefore any court stepT16, T21Not engaged
T24S0 End Stage Report; S1 Stage Plan; Business Case updatePM16 DecT16, T21Not started
T25Gate G0: approve, revise or stopExecutive18 DecT24Planned

S1 outline (route mapping and request execution)

Starts after G0

Start: After G0 (18 Dec 2026). Entry condition: G0 approval; free routes answered or overdue. Products: Custodian and route matrix (WP-OQ-01/02); complaint pathways (WP-OQ-03); court-application options paper (WP-OQ-04); timeframe estimate (WP-OQ-05); Reviews and ICO complaints on refusals (26-0010, 27589 if pursued); paid copies approved at G0; custodian and route matrix; legal triage paper. Dates and costs: Set at G0.

PRINCE2 7 outlines: sources · product set · archive