Work Packages
The Project Office › Parcel A (Phase 1) › Work Packages
- Work packages 22
Each work package below uses the PRINCE2 7 work package outline. “Not recorded” marks a field the original entry did not hold.
Work package status, 21 October 2026
17 work packages · GREEN 9 · AMBER 7 · RED 1
| Work package | Title | Team Manager | Tolerances | Status (RAG) | Target date | Notes |
|---|---|---|---|---|---|---|
| WP-PRESS | Press tip-off for the 22 Oct council meeting | AI worker (press) | Time: Sends must start before 22 Oct 19:00 Quality: Every figure cited; AI disclosed on every call; nothing non-public shared Scope: Welsh news, TV and radio newsdesks, community pages, citizen journalists; no direct messages (not connected) | AMBER Prepared; awaiting GO (D-01) | 22 Oct 2026 17:00 | 51 outlets, 35 newsdesk emails, 23 phones, 14 tip forms. Email and 30-second call script at version 5, checked. |
| WP-WT | Watchtower backfill to 2016 | AI worker (Watchtower) | Time: +1 day Quality: Each point links to its source or Wayback item Scope: Farm, 1987 case and Llandough items only | AMBER Running | 22 Oct 2026 | Earliest: 23 Mar 2016, 5 Apr 2016, 16 Aug 2016. Gmail 2019–2024 pass slow (about 45 s per call). |
| WP-HUB | HubSpot catch-up from Gmail | AI worker (CRM) | Time: +1 day Quality: No duplicates; officials by role and work email only Scope: Case threads since the last sync | AMBER Running | 22 Oct 2026 | Rate-limited (429s). Doughty recorded as MP of record. |
| WP-DISC-A | Disclosure trail Part A (Gmail → Wayback → wiki evidence → email archive → dartboard) | AI worker (disclosure A) | Time: +2 days Quality: Every number from the inventory; nothing rounded Scope: Institution disclosure threads | AMBER Inventory done; archiving and building | 23 Oct 2026 | 52 institutions, 257 conversations, 823 emails. 73 no reply; 8 statutory clocks missed with no reply. About 29 emails missing from the email archive being added. |
| WP-DISC-B | Disclosure trail Part B (WhatDoTheyKnow) | AI worker (disclosure B) | Time: Met Quality: Met Scope: 7 farm requests (2 unrelated excluded) | GREEN Complete | 21 Oct 2026 | 7 requests, 43 messages, 17 attachments; 3 refusals; 8 “not held”; 6 of 16 deadlines missed; 254 days waited. |
| WP-LIB | Library (free v0.01 e-books) | AI worker (library) | Time: Met Quality: 42 thin titles labelled as thin Scope: 121 books | GREEN Complete; follow-ups open | 21 Oct 2026 | Open: storage API errors; stale “In preparation” text; EV-0223 and EV-0255 lack fields (I-062). |
| WP-DIR | Directory (Llandough and Leckwith only) | AI worker (directory) | Time: Met Quality: In-area organisations only Scope: 307 entries | GREEN Complete | 21 Oct 2026 | Coverage now phone 124 / email 52 / website 122; 20 out-of-area entries removed. |
| WP-FB | farmbook (art and culture retelling) | AI worker (farmbook) | Time: Met Quality: Public-record roles only; no private data Scope: 30 profiles, 7 place plaques, 8 stories | GREEN Complete; gaps listed | 21 Oct 2026 | Gaps: Roman villa, OS field 71, the Vaughans, maps story. |
| WP-PRINTIFY | Printify and crest withdrawal | AI worker (shop) | Time: +4 days Quality: Nothing deleted Scope: Crest and arms off every site and product | AMBER Mostly complete | 25 Oct 2026 | 4 crest products hidden; 5 stale listings await D-07; printed items await Stripe verification. |
| WP-REOPEN | Reopen-loop (prospective triggers, every 4 h) | AI worker (research) | Time: Recurring Quality: Fixed Takhar test; primary sources only above score 2 Scope: Grounds to reopen the 1987 judgment | GREEN Running | Recurring; review at G0 | 49 experiments to 21 Oct. None meets the court-readiness bar. |
| WP-FLY | Research flywheel (every 6 h, update to the Executive) | AI worker (research) | Time: Recurring Quality: Sources named; unchecked items marked Scope: New evidence not yet on the sites | GREEN Running | Recurring | Next run 21:16, 21 Oct. |
| WP-DRAFTS | Nightly drafts engine (05:30) | AI worker (drafts) | Time: Recurring Quality: Drafts only; holds respected Scope: Chasers and replies | GREEN Running | Recurring | First run 21 Oct: 7 drafts. Council hold until 23 Oct. |
| WP-SEND | Reply sprint (final word rule) | AI worker (send) | Time: +1 week Quality: In-thread; no re-asking Scope: Every farm thread expecting a reply | AMBER 23 sent 21 Oct; about 155 older threads unchecked | 7 Nov 2026 | See I-057. |
| WP-EBOOK | E-book sales and promotion | AI worker (promo) | Time: Recurring Quality: Honest content; no fake reviews Scope: Facebook page; YouTube/TikTok when connected | RED 0 sales to date | Review 29 Oct 2026 | Stripe: 0 completed checkouts; Gumroad: 0. 26 Reels scheduled 21–29 Oct; captions carry the old price (I-065). |
| WP-HEALTH | Site health and wiki tables | AI worker (site flywheel) | Time: +2 days Quality: Verified live at 390 px Scope: All sites | AMBER About 249 of 727 wiki tables done; batch may have stopped | 23 Oct 2026 | See I-067. |
| WP-P2 | PRINCE2 housekeeping (this site) | Project Manager | Time: 21–22 Oct Quality: Every concern recorded; registers linked; verified live Scope: projects site; PRINCE2 off the Legal Wiki; HubSpot mirror | GREEN Running | 22 Oct 2026 | Registers, checkpoint report, HR-05 and Archive published 21 Oct. |
| WP-REOPEN | Side project: reopen the case (SOP readiness and filing) | Project Manager | Time: Standby until a trigger; then Gate 3 by T0 + 8 weeks; no legal time limit missed Quality: Every document hashed and logged from T0; every limit cited to its rule Scope: /sop-trigger-event/, /side-project-reopen/, sop-branches.json; filing only after a written opinion | GREEN Standby | Clock-driven (T0 + 8 weeks to Gate 3) | SOP v1 published 21 Oct 2026: trigger-event SOP, side project; awaiting D-19. |
WP-FLY
Research cycle report; EV proposals · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: Every 6 h (next 03:16) |
| Authorised by | Executive |
| Team manager or person authorised | Project Manager research worker |
| Work package description | Research cycle report; EV proposals |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: Every 6 h (next 03:16) |
| Tolerances | ≈45 min; read-only; graph ≤$3 |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Report saved; Executive updated (new, cuts-against, asks) |
WP-SEND
Sent emails; HubSpot updates · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: Weekdays 09:20, until all READY sent |
| Authorised by | Executive |
| Team manager or person authorised | Project Manager send worker |
| Work package description | Sent emails; HubSpot updates |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: Weekdays 09:20, until all READY sent |
| Tolerances | ≤1 per body per day; office hours |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | PD-07 met; in Sent; task closed; Executive told |
WP-DEBRIEF
All surfaces brought up to date · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: On the Executive’s word “run the debrief flywheel” |
| Authorised by | Executive |
| Team manager or person authorised | Project Manager debrief worker |
| Work package description | All surfaces brought up to date |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: On the Executive’s word “run the debrief flywheel” |
| Tolerances | Never sends email; backups first |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | PD-08 met; 5-line summary |
WP-CAT
EV pages and Register rows · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: After each cycle with finds |
| Authorised by | Executive |
| Team manager or person authorised | Project Manager catalogue worker |
| Work package description | EV pages and Register rows |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: After each cycle with finds |
| Tolerances | Next free EV-0244 |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Live; cuts-against; Change Log row |
WP-WG
WG combined reply draft · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: Draft 19 Oct; send 21 Oct 10:00 |
| Authorised by | Executive |
| Team manager or person authorised | Project Manager drafts worker |
| Work package description | WG combined reply draft |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: Draft 19 Oct; send 21 Oct 10:00 |
| Tolerances | No send without check |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Draft fits both 19 Oct letters |
WP-05.A
HMLR copies via SAR · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: SAR due 28 Oct |
| Authorised by | Executive |
| Team manager or person authorised | Executive; HMLR |
| Work package description | HMLR copies via SAR |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: SAR due 28 Oct |
| Tolerances | OC2 only for refusals |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Copies held; EV set HELD |
WP-39.A
ICR full complaint · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: 13 Nov |
| Authorised by | Executive |
| Team manager or person authorised | Executive; Project Manager drafts |
| Work package description | ICR full complaint |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: 13 Nov |
| Tolerances | Control 18 Nov |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | PD-04 met |
WP-LCC-22
LCC meeting Item 10 · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: 22 Oct; minutes 29 Oct |
| Authorised by | Executive |
| Team manager or person authorised | Executive |
| Work package description | LCC meeting Item 10 |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: 22 Oct; minutes 29 Oct |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Outcome and lessons published |
WP-LEGAL
Legal triage · Running (recurring)
| Field | Entry |
|---|---|
| Date | Cadence: Before any court step |
| Authorised by | Executive |
| Team manager or person authorised | Executive |
| Work package description | Legal triage |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Cadence: Before any court step |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Written route decision |
WP-05.A
HMLR official copies C-01 to C-06 · Proposed
| Field | Entry |
|---|---|
| Date | Start 19 Oct; due 19 Oct (order) |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | HMLR official copies C-01 to C-06 |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 19 Oct; due 19 Oct (order) |
| Tolerances | Cost £66; time +0 |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Copies held; EV pages set HELD |
WP-05.B
Form 1C analysis; title chain update (AC-006) · Proposed
| Field | Entry |
|---|---|
| Date | Start Copies in; due +3 days |
| Authorised by | Not recorded |
| Team manager or person authorised | Project Manager |
| Work package description | Form 1C analysis; title chain update (AC-006) |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start Copies in; due +3 days; predecessor WP-05.A |
| Tolerances | Time +2 days |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Every finding cites the copy; I-004 updated |
WP-39.A
ICR full complaint, ICR/090/26 (PD-04) · Proposed
| Field | Entry |
|---|---|
| Date | Start 2 Nov; due 13 Nov (target) |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive; Project Manager drafts |
| Work package description | ICR full complaint, ICR/090/26 (PD-04) |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 2 Nov; due 13 Nov (target); predecessor WP-05.B |
| Tolerances | Hard stop 18 Nov control / ~25 Nov outer |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | PD-04 criteria met; sent by Executive |
WP-01.A
1965 school conveyance (Vale FOI 00211027) to the wiki · Proposed
| Field | Entry |
|---|---|
| Date | Start 19 Oct; due 21 Oct |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | 1965 school conveyance (Vale FOI 00211027) to the wiki |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 19 Oct; due 21 Oct |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | PDF uploaded; [PENDING: EV-0042] set HELD |
WP-02.A
DB/E/1–2 plan 19 and terrier · Proposed
| Field | Entry |
|---|---|
| Date | Start 19 Oct; due TBC |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | DB/E/1–2 plan 19 and terrier |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 19 Oct; due TBC |
| Tolerances | Cost £17 |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Images held; map identity settled (R-012) |
WP-VG
VG41 register sheet and present title · Open
| Field | Entry |
|---|---|
| Date | Start TBC; due TBC |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | VG41 register sheet and present title |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start TBC; due TBC |
| Tolerances | Cost TBC |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Entry, map and ownership section held [PENDING: EV-0044] |
WP-LCC-22
Llandough CC meeting, Item 10 · Open
| Field | Entry |
|---|---|
| Date | Start 16 Oct; due 29 Oct |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | Llandough CC meeting, Item 10 |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 16 Oct; due 29 Oct; predecessor T06 |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Minutes, outcome and lessons published |
WP-10.A
Council s.12: narrow or internal review · Proposed
| Field | Entry |
|---|---|
| Date | Start 23 Oct; due TBC |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | Council s.12: narrow or internal review |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 23 Oct; due TBC; predecessor WP-LCC-22 |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Decision recorded; request sent |
WP-FLY
Research flywheel (every 6 h) · Running
| Field | Entry |
|---|---|
| Date | Start 16 Oct; due 18 Dec |
| Authorised by | Executive |
| Team manager or person authorised | Project Manager |
| Work package description | Research flywheel (every 6 h) |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 16 Oct; due 18 Dec |
| Tolerances | Read-only; no contact |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Update to Executive after each cycle |
WP-LEGAL
Solicitor/counsel route triage · Status to be confirmed by the Executive
| Field | Entry |
|---|---|
| Date | Start —; due 12 Oct (planned) |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | Solicitor/counsel route triage |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start —; due 12 Oct (planned); predecessor WP-05.B |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Written route decision |
WP-31
Counsel’s early case assessment · Open
| Field | Entry |
|---|---|
| Date | Start —; due Instructions by 26 Mar 2027 |
| Authorised by | Not recorded |
| Team manager or person authorised | Executive |
| Work package description | Counsel’s early case assessment |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start —; due Instructions by 26 Mar 2027; predecessor WP-LEGAL |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Assessment received |
WP-OQ-01 to 05
Custodian register; route matrix; complaint pathways; court options; timeframe · Authorised 16 Oct
| Field | Entry |
|---|---|
| Date | Start 16 Oct; due S1 |
| Authorised by | Not recorded |
| Team manager or person authorised | PM |
| Work package description | Custodian register; route matrix; complaint pathways; court options; timeframe |
| Techniques, processes and procedures | Back up first; delete nothing; verify live; log every change. |
| Development interfaces | Not recorded |
| Operations and maintenance interfaces | Not recorded |
| Change control requirements | Every product filed as an evidence page or management product (Product Register). |
| Joint agreements | Start 16 Oct; due S1 |
| Tolerances | — |
| Constraints | Research support only; no spending or orders without the Executive. |
| Reporting arrangements | Checkpoint at each research cycle; issues to the Issue Register. |
| Problem handling and escalation | To the Project Manager; tolerance breaches to the Executive the same day. |
| Extracts or references | Product Descriptions |
| Approval method | Outputs per Plan (16 Oct) |
PRINCE2 7 outlines: sources · product set · archive