Work Packages

The Project Office › Parcel A (Phase 1) › Work Packages

Each work package below uses the PRINCE2 7 work package outline. “Not recorded” marks a field the original entry did not hold.

Work package status, 21 October 2026

17 work packages · GREEN 9 · AMBER 7 · RED 1
Work packageTitleTeam ManagerTolerancesStatus (RAG)Target dateNotes
WP-PRESSPress tip-off for the 22 Oct council meetingAI worker (press)Time: Sends must start before 22 Oct 19:00
Quality: Every figure cited; AI disclosed on every call; nothing non-public shared
Scope: Welsh news, TV and radio newsdesks, community pages, citizen journalists; no direct messages (not connected)
AMBER Prepared; awaiting GO (D-01)22 Oct 2026 17:0051 outlets, 35 newsdesk emails, 23 phones, 14 tip forms. Email and 30-second call script at version 5, checked.
WP-WTWatchtower backfill to 2016AI worker (Watchtower)Time: +1 day
Quality: Each point links to its source or Wayback item
Scope: Farm, 1987 case and Llandough items only
AMBER Running22 Oct 2026Earliest: 23 Mar 2016, 5 Apr 2016, 16 Aug 2016. Gmail 2019–2024 pass slow (about 45 s per call).
WP-HUBHubSpot catch-up from GmailAI worker (CRM)Time: +1 day
Quality: No duplicates; officials by role and work email only
Scope: Case threads since the last sync
AMBER Running22 Oct 2026Rate-limited (429s). Doughty recorded as MP of record.
WP-DISC-ADisclosure trail Part A (Gmail → Wayback → wiki evidence → email archive → dartboard)AI worker (disclosure A)Time: +2 days
Quality: Every number from the inventory; nothing rounded
Scope: Institution disclosure threads
AMBER Inventory done; archiving and building23 Oct 202652 institutions, 257 conversations, 823 emails. 73 no reply; 8 statutory clocks missed with no reply. About 29 emails missing from the email archive being added.
WP-DISC-BDisclosure trail Part B (WhatDoTheyKnow)AI worker (disclosure B)Time: Met
Quality: Met
Scope: 7 farm requests (2 unrelated excluded)
GREEN Complete21 Oct 20267 requests, 43 messages, 17 attachments; 3 refusals; 8 “not held”; 6 of 16 deadlines missed; 254 days waited.
WP-LIBLibrary (free v0.01 e-books)AI worker (library)Time: Met
Quality: 42 thin titles labelled as thin
Scope: 121 books
GREEN Complete; follow-ups open21 Oct 2026Open: storage API errors; stale “In preparation” text; EV-0223 and EV-0255 lack fields (I-062).
WP-DIRDirectory (Llandough and Leckwith only)AI worker (directory)Time: Met
Quality: In-area organisations only
Scope: 307 entries
GREEN Complete21 Oct 2026Coverage now phone 124 / email 52 / website 122; 20 out-of-area entries removed.
WP-FBfarmbook (art and culture retelling)AI worker (farmbook)Time: Met
Quality: Public-record roles only; no private data
Scope: 30 profiles, 7 place plaques, 8 stories
GREEN Complete; gaps listed21 Oct 2026Gaps: Roman villa, OS field 71, the Vaughans, maps story.
WP-PRINTIFYPrintify and crest withdrawalAI worker (shop)Time: +4 days
Quality: Nothing deleted
Scope: Crest and arms off every site and product
AMBER Mostly complete25 Oct 20264 crest products hidden; 5 stale listings await D-07; printed items await Stripe verification.
WP-REOPENReopen-loop (prospective triggers, every 4 h)AI worker (research)Time: Recurring
Quality: Fixed Takhar test; primary sources only above score 2
Scope: Grounds to reopen the 1987 judgment
GREEN RunningRecurring; review at G049 experiments to 21 Oct. None meets the court-readiness bar.
WP-FLYResearch flywheel (every 6 h, update to the Executive)AI worker (research)Time: Recurring
Quality: Sources named; unchecked items marked
Scope: New evidence not yet on the sites
GREEN RunningRecurringNext run 21:16, 21 Oct.
WP-DRAFTSNightly drafts engine (05:30)AI worker (drafts)Time: Recurring
Quality: Drafts only; holds respected
Scope: Chasers and replies
GREEN RunningRecurringFirst run 21 Oct: 7 drafts. Council hold until 23 Oct.
WP-SENDReply sprint (final word rule)AI worker (send)Time: +1 week
Quality: In-thread; no re-asking
Scope: Every farm thread expecting a reply
AMBER 23 sent 21 Oct; about 155 older threads unchecked7 Nov 2026See I-057.
WP-EBOOKE-book sales and promotionAI worker (promo)Time: Recurring
Quality: Honest content; no fake reviews
Scope: Facebook page; YouTube/TikTok when connected
RED 0 sales to dateReview 29 Oct 2026Stripe: 0 completed checkouts; Gumroad: 0. 26 Reels scheduled 21–29 Oct; captions carry the old price (I-065).
WP-HEALTHSite health and wiki tablesAI worker (site flywheel)Time: +2 days
Quality: Verified live at 390 px
Scope: All sites
AMBER About 249 of 727 wiki tables done; batch may have stopped23 Oct 2026See I-067.
WP-P2PRINCE2 housekeeping (this site)Project ManagerTime: 21–22 Oct
Quality: Every concern recorded; registers linked; verified live
Scope: projects site; PRINCE2 off the Legal Wiki; HubSpot mirror
GREEN Running22 Oct 2026Registers, checkpoint report, HR-05 and Archive published 21 Oct.
WP-REOPENSide project: reopen the case (SOP readiness and filing)Project ManagerTime: Standby until a trigger; then Gate 3 by T0 + 8 weeks; no legal time limit missed
Quality: Every document hashed and logged from T0; every limit cited to its rule
Scope: /sop-trigger-event/, /side-project-reopen/, sop-branches.json; filing only after a written opinion
GREEN StandbyClock-driven (T0 + 8 weeks to Gate 3)SOP v1 published 21 Oct 2026: trigger-event SOP, side project; awaiting D-19.

WP-FLY

Research cycle report; EV proposals · Running (recurring)
FieldEntry
DateCadence: Every 6 h (next 03:16)
Authorised byExecutive
Team manager or person authorisedProject Manager research worker
Work package descriptionResearch cycle report; EV proposals
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: Every 6 h (next 03:16)
Tolerances≈45 min; read-only; graph ≤$3
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodReport saved; Executive updated (new, cuts-against, asks)

WP-SEND

Sent emails; HubSpot updates · Running (recurring)
FieldEntry
DateCadence: Weekdays 09:20, until all READY sent
Authorised byExecutive
Team manager or person authorisedProject Manager send worker
Work package descriptionSent emails; HubSpot updates
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: Weekdays 09:20, until all READY sent
Tolerances≤1 per body per day; office hours
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodPD-07 met; in Sent; task closed; Executive told

WP-DEBRIEF

All surfaces brought up to date · Running (recurring)
FieldEntry
DateCadence: On the Executive’s word “run the debrief flywheel”
Authorised byExecutive
Team manager or person authorisedProject Manager debrief worker
Work package descriptionAll surfaces brought up to date
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: On the Executive’s word “run the debrief flywheel”
TolerancesNever sends email; backups first
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodPD-08 met; 5-line summary

WP-CAT

EV pages and Register rows · Running (recurring)
FieldEntry
DateCadence: After each cycle with finds
Authorised byExecutive
Team manager or person authorisedProject Manager catalogue worker
Work package descriptionEV pages and Register rows
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: After each cycle with finds
TolerancesNext free EV-0244
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodLive; cuts-against; Change Log row

WP-WG

WG combined reply draft · Running (recurring)
FieldEntry
DateCadence: Draft 19 Oct; send 21 Oct 10:00
Authorised byExecutive
Team manager or person authorisedProject Manager drafts worker
Work package descriptionWG combined reply draft
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: Draft 19 Oct; send 21 Oct 10:00
TolerancesNo send without check
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodDraft fits both 19 Oct letters

WP-05.A

HMLR copies via SAR · Running (recurring)
FieldEntry
DateCadence: SAR due 28 Oct
Authorised byExecutive
Team manager or person authorisedExecutive; HMLR
Work package descriptionHMLR copies via SAR
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: SAR due 28 Oct
TolerancesOC2 only for refusals
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodCopies held; EV set HELD

WP-39.A

ICR full complaint · Running (recurring)
FieldEntry
DateCadence: 13 Nov
Authorised byExecutive
Team manager or person authorisedExecutive; Project Manager drafts
Work package descriptionICR full complaint
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: 13 Nov
TolerancesControl 18 Nov
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodPD-04 met

WP-LCC-22

LCC meeting Item 10 · Running (recurring)
FieldEntry
DateCadence: 22 Oct; minutes 29 Oct
Authorised byExecutive
Team manager or person authorisedExecutive
Work package descriptionLCC meeting Item 10
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsCadence: 22 Oct; minutes 29 Oct
Tolerances—
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodOutcome and lessons published

WP-05.A

HMLR official copies C-01 to C-06 · Proposed
FieldEntry
DateStart 19 Oct; due 19 Oct (order)
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package descriptionHMLR official copies C-01 to C-06
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 19 Oct; due 19 Oct (order)
TolerancesCost £66; time +0
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodCopies held; EV pages set HELD

WP-05.B

Form 1C analysis; title chain update (AC-006) · Proposed
FieldEntry
DateStart Copies in; due +3 days
Authorised byNot recorded
Team manager or person authorisedProject Manager
Work package descriptionForm 1C analysis; title chain update (AC-006)
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart Copies in; due +3 days; predecessor WP-05.A
TolerancesTime +2 days
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodEvery finding cites the copy; I-004 updated

WP-39.A

ICR full complaint, ICR/090/26 (PD-04) · Proposed
FieldEntry
DateStart 2 Nov; due 13 Nov (target)
Authorised byNot recorded
Team manager or person authorisedExecutive; Project Manager drafts
Work package descriptionICR full complaint, ICR/090/26 (PD-04)
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 2 Nov; due 13 Nov (target); predecessor WP-05.B
TolerancesHard stop 18 Nov control / ~25 Nov outer
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodPD-04 criteria met; sent by Executive

WP-01.A

1965 school conveyance (Vale FOI 00211027) to the wiki · Proposed
FieldEntry
DateStart 19 Oct; due 21 Oct
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package description1965 school conveyance (Vale FOI 00211027) to the wiki
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 19 Oct; due 21 Oct
Tolerances—
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodPDF uploaded; [PENDING: EV-0042] set HELD

WP-02.A

DB/E/1–2 plan 19 and terrier · Proposed
FieldEntry
DateStart 19 Oct; due TBC
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package descriptionDB/E/1–2 plan 19 and terrier
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 19 Oct; due TBC
TolerancesCost £17
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodImages held; map identity settled (R-012)

WP-VG

VG41 register sheet and present title · Open
FieldEntry
DateStart TBC; due TBC
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package descriptionVG41 register sheet and present title
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart TBC; due TBC
TolerancesCost TBC
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodEntry, map and ownership section held [PENDING: EV-0044]

WP-LCC-22

Llandough CC meeting, Item 10 · Open
FieldEntry
DateStart 16 Oct; due 29 Oct
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package descriptionLlandough CC meeting, Item 10
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 16 Oct; due 29 Oct; predecessor T06
Tolerances—
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodMinutes, outcome and lessons published

WP-10.A

Council s.12: narrow or internal review · Proposed
FieldEntry
DateStart 23 Oct; due TBC
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package descriptionCouncil s.12: narrow or internal review
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 23 Oct; due TBC; predecessor WP-LCC-22
Tolerances—
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodDecision recorded; request sent

WP-FLY

Research flywheel (every 6 h) · Running
FieldEntry
DateStart 16 Oct; due 18 Dec
Authorised byExecutive
Team manager or person authorisedProject Manager
Work package descriptionResearch flywheel (every 6 h)
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 16 Oct; due 18 Dec
TolerancesRead-only; no contact
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodUpdate to Executive after each cycle

WP-31

Counsel’s early case assessment · Open
FieldEntry
DateStart —; due Instructions by 26 Mar 2027
Authorised byNot recorded
Team manager or person authorisedExecutive
Work package descriptionCounsel’s early case assessment
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart —; due Instructions by 26 Mar 2027; predecessor WP-LEGAL
Tolerances—
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodAssessment received

WP-OQ-01 to 05

Custodian register; route matrix; complaint pathways; court options; timeframe · Authorised 16 Oct
FieldEntry
DateStart 16 Oct; due S1
Authorised byNot recorded
Team manager or person authorisedPM
Work package descriptionCustodian register; route matrix; complaint pathways; court options; timeframe
Techniques, processes and proceduresBack up first; delete nothing; verify live; log every change.
Development interfacesNot recorded
Operations and maintenance interfacesNot recorded
Change control requirementsEvery product filed as an evidence page or management product (Product Register).
Joint agreementsStart 16 Oct; due S1
Tolerances—
ConstraintsResearch support only; no spending or orders without the Executive.
Reporting arrangementsCheckpoint at each research cycle; issues to the Issue Register.
Problem handling and escalationTo the Project Manager; tolerance breaches to the Executive the same day.
Extracts or referencesProduct Descriptions
Approval methodOutputs per Plan (16 Oct)

PRINCE2 7 outlines: sources · product set · archive