Business Case

The Project Office › Parcel A (Phase 1) › Business Case

Justification for Parcel A (Phase 1). Outline 18 October 2026; current baseline 19 October; reviewed at gate G0.

Executive summary

Free routes first; £0 spent; review at G0

Recovering, or formally ruling out, every surviving record is the precondition for any title, remedy or accountability route. Option 1 (free routes first) was selected on 18 October; cash spent in the project is £0. The return is non-financial until reparations can be quantified. The case is reviewed at G0 (18 December 2026): continue, revise or stop.

Reasons

Recover or rule out every record

The Mandate (16 Oct 2026) requires every surviving record recovered or formally ruled out. The aim behind it is to reopen BP Properties Ltd v Buckler [1987] EWCA Civ 2 and seek reparations; that needs evidence meeting the Takhar v Gracefield [2019] UKSC 13 test or concealment under the Limitation Act 1980 s.32 (Canada Square v Potter [2023] UKSC 41). This is our case,

Business options

0 do nothing · 1 free routes (selected) · 2 paid copies · 3 court
OptionContentCostAssessment
0 Do nothingStop£0Key records stay unseen; no reopen decision possible
1 Free admin firstFOI/EIR, SAR, complaints, reviews, ICR, free archive enquiries£0 cash; the Executive’s timeSELECTED (Executive, 18 Oct 23:40)
2 Paid copies and visitsOption 1 plus HMLR OC2 for what is refused, archive copiesAbout £83–£313 + TBC (Plan C-01–C-20)After free routes are answered; each spend approved
3 Court applicationSet-aside / limitation routeUnquantifiedOnly after written legal advice (DEP-03)

Expected benefits

B-01 to B-05
IDBenefitMeasureWhen
B-01Auditable evidence position% of identified items with a closure statusEnd S3
B-02Remedy route can be assessedForm 1C and 1905 deed held and analysedBefore ICR complaint (13 Nov)
B-03Public record traceable% of key statements citing an EV pageEach Highlight
B-04Reopen decisionWritten legal triage on the evidenceG0 or later
B-05Reparations claim quantifiedHeads on 5298 firm, not indicativeAfter DMG-IN inputs

Expected dis-benefits

3 dis-benefits
  • The Executive’s time.
  • Family matters on a public record.
  • Findings that cut against the case are published too (e.g. H15 scored 1/5 on 18 Oct).

Timescale

To G0, 18 Dec 2026

S0 to G0, 18 December 2026. Later stages dated at G0.

Costs

£0 spent; S0 envelope proposed £0–£800
ItemAmountStatus
Cash spent to date£0No purchases on Project Manager’s ledger
Free routes (FOI/EIR/SAR/complaints)£0In progress: 24 emails scheduled 20–23 Oct
HMLR OC2, only for what HMLR refuses£11 per documentNot ordered (CH-012, CH-013)
Archive copies (e.g. DB/E/1 £17)Per quoteOn hold
S0 cost tolerance£0–£800Within

Detail: Project Plan, budgets.

Investment appraisal

Non-financial

Non-financial until reparations can be quantified. No monetary return is stated.

Major risks

R-008, R-019, R-022, R-017, R-018

R-008 limitation; R-019 liability in emails; R-022 tenancy evidence; R-017 repeat-request refusals; R-018 destroyed records; R-002, R-007. Risk Register.

PRINCE2 7 outlines: sources · product set · archive