Highlight Report HR-01
The Project Office › Parcel A (Phase 1) › Highlight Reports › HR-01
- Date 18 October 2026
- Period 5–17 October 2026
- Status AMBER
Date
18 October 2026
18 October 2026
Period covered
5–17 October 2026
5–17 October 2026
Status summary
AMBER Stage S0 (start-up and initiation); next gate G0 forecast 18 December 2026. Deadlines in hand; £0 spent in the week to 18 October; HM Land Registry copies (form OC2) not yet ordered.
Combines the former HR-01, the “week ending 18 October” report and the 8 and 17 October addenda, so that each period has one report.
This reporting period
20 entries
Work packages
Pending authorisation
None this period.
In execution
- Records requests and reviews: 83 draft requests reviewed, 14 ready; four EIR drafts prepared (Cardiff Council, Welsh Government, Vale of Glamorgan, Glamorgan Archives).
- Litigation activation (from 8 Oct): 20 new execution tasks covering solicitor triage, filings and notices, archive visits, court-file recovery, disclosure and preservation, the ICR, current title, public-authority escalation and recollection indexing.
- County Treasures inventory request (late-1970s South Glamorgan inventory, Great House Farm / Tŷ Mawr entry) drafted 17 Oct and held for review; not sent.
- Cross-institution contradiction packs staged 17 Oct for several bodies; all drafts, none sent.
Completed in the period
None this period.
Products completed in the period
- Evidence Register: 210 EV pages (105 held, 105 pending), 18 Oct.
- Claim audit: 445 statements on 30 pages (168 held, 181 pending, 96 hypothesis), 18 Oct.
- EV-0216: the 1965 deed names the Western Ground Rents root, “a Conveyance on sale dated 25th December 1938”.
- EV-0217: Forest of Cardiff accounts to 30 June 2006, “Sale of Land — Leckwith Road, Llandough 20,000”.
- EV-0218 to EV-0221: Cwm Cydfin SSSI 0524 (notified 1972 and 9 Dec 1985; 5.5 ha); Bute coppice-woods sale 29 Nov 1902; Western Ground Rents 1938 purchase and about 109 acres of Leckwith Woods to Cardiff, 1940–42 (secondary sources). Overlap with WA735527 or plan 19 not established.
- Woodland and land-transfer assessment 1902–2005 published.
- Correspondence pages: 20 published, 18 trimmed to farm-case content; institutions’ replies verbatim.
- Corrections: 1939 wording (I-008); judgment date 24 July 1986 (I-012); 1958 citation (I-013).
- Estate run E1: map probably Glamorgan Archives DB/E/1 plan 19 (Stewart, 1824); catalogue match only, not yet checked against the original.
- Institution review pages replaced by evidence-specific reviews (8 Oct).
- PRINCE2 document set rebuilt (CH-008).
Products planned but not started or completed in the period
- HM Land Registry OC2 copies C-01 to C-06: deferred (fees).
- EV-0222 (DBDT121/3, Western Ground Rents–Coles tenancy, Leckwith, Oct 1944): pending.
- The 1965 conveyance to be added to EV-0042: pending.
Corrective actions taken during the period
- D696 Western Ground Rents rent books reclassified as background corroboration only; no archive visit unless a direct Parcel A lead appears (8 Oct).
- Personal passages trimmed from published correspondence; hypotheses labelled.
Next reporting period
7 entries
Work packages (to be authorised, in execution, to be completed)
- Send ready requests in three batches, 1–2 per body per day; clear superseded drafts (from 19 Oct).
Products to be completed in the next period
- 20 Oct: bona vacantia FOI (Government Legal Department); EIR 1 of 4, Cardiff Council 1942 conveyance and plan.
- 21 Oct: EIR 2 of 4, Welsh Government, Land Authority for Wales 1988 file; free HM Land Registry map search.
- 22 Oct: EIR 3 of 4, Vale of Glamorgan 1994 transfer and green register; Llandough Community Council meeting, Item 10, 19:00.
- 23 Oct: EIR 4 of 4, Glamorgan Archives 1940–42 minute references.
- 29 Oct: meeting minutes, outcome and lessons published.
Corrective actions to be completed during the next period
- On hold for fees: OC2 copies C-01 to C-06; RCAHMW scans; DB/E/1 plan 19.
Project and stage tolerance status
Tolerances not yet agreed by the Project Board
| Tolerance area | Tolerance set | Status this period |
|---|---|---|
| Time | Not yet agreed by the Project Board | Within. ICR date basis unconfirmed (I-010); OC2 copies deferred puts the ICR path at risk (R-007). |
| Cost | Not yet agreed by the Project Board | Within. £0 spent in the week to 18 Oct; one copy at £14 recorded earlier (C-21). |
| Quality | Not yet agreed by the Project Board | Within after corrections I-008, I-012, I-013. |
| Scope | Not yet agreed by the Project Board | Changed by CH-004 (approved); land-transfer route and correspondence pages added. |
| Benefits | Not yet agreed by the Project Board | Not yet set by the Executive. |
| Risk | Not yet agreed by the Project Board | R-002, R-007, R-008 high impact. |
| Sustainability | Not yet agreed by the Project Board | Not assessed. |
Requests for change
2 raised · 1 decided · 2 pending
Raised
- CH-009 footer policy.
- CH-011 WordPress plan.
Approved or rejected
- CH-004 scope change: approved.
Pending
- CH-009 footer policy.
- CH-011 WordPress plan.
Key issues and risks
7 items
- R-007 / R-002: OC2 copies (£11 each, published fee) deferred; Form 1C is on the ICR critical path. Exception Report due if the copies are not in hand by 6 Nov.
- Hypothesis H-WGR-1940 (the 1940–42 gift took Parcel A) scored 0/5: every report found reads “at Leckwith”. Against the case: Bute sold the Cwm Cydfin wood as owner in 1902; the SSSI lies outside the farmhouse parcel.
- R-004: several requests to one body at once; space new requests.
- R-010 WordPress connection (about mid-November); R-013 damages figures stay indicative until the damages inputs arrive.
- Open issues: I-006 footer decision; I-007 Project Manager role; I-010 ICR date basis; I-011 meeting format; I-014 s.12 options; I-015 to I-019 damages inputs.
- Decisions requested from the Executive: damages inputs I-015 to I-019 (hours and periods worked; medical evidence; livestock, business, contents and rehousing losses; living claimants and grants of probate; areas of Parcel A’s three parts); publish or hold the press and solicitors correspondence pages; ICR next step; approval of the four EIR requests; hold or order the OC2 copies.
- Deadlines: 26 Oct ATISN 27589, IR/26/16, Vale 00211557; 28 Oct HM Land Registry subject access request; 29 Oct ICO complaint if unresolved; 6 Nov exception trigger (R-007); 9 Nov South Wales Police FOI 1264/26; 13 Nov ICR target, about 25 Nov outer date.
Lessons report (if appropriate)
4 lessons
- L-006 to L-009 (Lessons Log).
- Check a platform’s limits before reporting a result (Facebook feed dates).
- Trim personal material before publishing correspondence.
- Research from other AI tools is a lead only (L-006).
← HR-2026-10A · All highlight reports · HR-02 →