Master Highlight Report

Dashboard · Mandate · Plan · Reports · P1 Museum · P2 Recovery · P3 AR Tour · P4 Legal Gate

Master highlight report — 22 October 2026

The programme is now represented as three active projects with separate products and measures, plus a conditional legal gate. No overall percentage is claimed because the current denominators cover different scopes. Preparing a project plan does not mean the museum or AR tour is nearly ready to open.

Project summary

Progress, current position and next action
ProjectMeasure/statusThis periodNext actions
P1 — Argentina replica museum17% of 12 starter tasks; actual museum delivery 0%. AMBERWorking brief and existing source corpus recognised as starting inputs. No site or build approval.Source confidence, room/landscape product schedule, then scoped feasibility and cost model.
P2 — Wales records and testimony recovery19% of 893-task ledger; denominator incomplete for full scope. AMBERRegistered state: 169 done, 44 in progress, 645 not started, 35 blocked. This does not measure the share of all records recovered.Preserve vulnerable items; keep FOI/EIR and archive routes current; integrate witness/source preservation tasks; reconcile parcel-level land/planning/heritage records.
P3 — Parcel A AR tour17% of 12 starter tasks; actual AR delivery 0%. AMBERResearch and visual story tour identified; no functioning AR model/prototype/pilot.Map route; verify Roman-villa/farm and early ecclesiastical locations; define confidence legend and low-cost prototype.
P4 — Legal remedyN/A; not initiated. STANDBYNo item recorded as having passed the activation gate.Continue preservation/trigger review within P2. Activate only after independent written legal review and Executive authorisation.

Principal risks and controls

Needs active management
  • R1 — Records become inaccessible: preserve originals or reliable copies, metadata, headers, plans and versions promptly. A missing response is not proof of destruction.
  • R2 — Incorrect site attribution: exact-site AR depictions need spatial source verification. Keep nearby archaeological features separate from Parcel A.
  • R3 — Museum feasibility and cost: Argentine site/title, permissions, services, climate response, capital and operating cost remain open. No land commitment before a gate.
  • R4 — P2 denominator: inherited 893-task measure does not include a fully normalised count for every preservation, witness and all-source task. Keep 19% clearly labelled until rebaseline.
  • R5 — Legal trigger overstatement: discrepancy, non-response or public-body involvement alone does not establish wrongdoing or a remedy. Require a source, materiality, independent legal review and written gate decision.
  • R6 — Assurance gap: independent Project Assurance is not appointed; preserve this limitation in reports and procure independent specialist review where a gate requires it.

Decisions requested

Not yet recorded as approved
  1. Approve, amend or reject the three-active-project structure and measurement method.
  2. Authorise bounded P1/P3 start-up tasks and set no-spend boundaries, owners and acceptance tests.
  3. Confirm P2 priorities for preservation, disclosure and witness material, plus the work to reconcile its full task denominator.
  4. Keep P4 dormant until its evidence/legal gate has passed.
  5. Confirm roles, project-level tolerances, independent assurance and next reporting checkpoint.

Next checkpoint proposed: 23 October 2026. No approval is inferred from this report.