PRINCE2 product set

The Project Office › Product set

The 31 PRINCE2 7 management products and which exist for Parcel A (Phase 1).

Baselines

17 of 18 present
ProductParcel ANote
Business casePresent—
Benefits management approachPresent—
Change management approachPresent—
Commercial management approachPresent—
Communication management approachPresent—
Digital and data management approachPresent—
Issue management approachPresent—
Quality management approachPresent—
Risk management approachPresent—
Sustainability management approachPresentPresent; content not yet set
Plan (project)Present—
Plan (stage)Present—
Plan (exception)PendingOnly if a tolerance is forecast to be exceeded
Product descriptionsPresent—
Project briefPresent—
Project initiation documentationPresent—
Project product descriptionPresent—
Work packagesPresent—

Project log

6 of 6 present
ProductParcel ANote
Daily logPresent—
Issue registerPresent—
Lessons logPresent—
Product registerPresent—
Quality registerPresent—
Risk registerPresent—

Reports

4 of 7 present
ProductParcel ANote
Checkpoint reportPresentCR-2026-10-21; research cycle reports also stand in (tailoring)
End project reportPendingAt project closure
End stage reportPresentS0 interim
Exception reportPendingFirst trigger: HM Land Registry copies not held by 6 Nov
Highlight reportPresent—
Issue reportPresent—
Lessons reportPendingAt stage end or closure

Other projects

4 projects
ProjectProducts present
Digital estateProject brief, business case, PID, stage plans, product descriptions, product register, risk, issue and quality registers, lessons log, highlight reports HR-E01 and HR-E02
Phase 2: Cedwyn EstateProject brief (not yet initiated)
Membership pilotProject brief
P4 · Tŷ Mawr replica and museumMuseum project brief, land reconnaissance, funding and partner plan, implementation roadmap

PRINCE2 7 outlines: sources · product set · archive